Mining Investigation Permits and Exploitation Concessions in Spain: Sections A to D, Deadlines, Fees, Restoration and Strategic Projects (Rare Earths, Lithium, Tungsten)

Last updated 15 October 2026 · Reviewed by Jaime Piñeira Pardo, lawyer registered with the ICAM bar, no. 138826 · English version of our Spanish guide.

The short answer

To investigate a rare earth, lithium or tungsten deposit in Spain, you need a Section C investigation permit: valid for up to 3 years, extendable, covering 1 to 300 mining grids, with a technical project and a restoration plan. Once the resource is proven, you apply for the exploitation concession before the permit expires: 30 years, extendable up to 90. Managora prepares and submits the application using your power of attorney.

We handle the whole procedure for you, from start to finish.

You describe your case in a chat and sign; we file it with the Spanish authorities. Fixed price from €399.00 (21% VAT included), plus the tasa (official fee) where there is one.

See the procedure

What is new, and the law that applies

  • 9 October 2026: the European Commission selects 46 new CRMA strategic projects across 16 Member States, 2 of them in Spain, and announces another call for late 2026.
  • 18 September 2026: Real Decreto 731/2026 enters into force, allowing critical raw material projects to be declared a Proyecto Estratégico de Inversión (Strategic Investment Project).
  • 18 April 2026: Orden TED/352/2026 enters into force, establishing the rules for grants under the Programa Nacional de Exploración Minera 2026-2030 (National Mining Exploration Programme 2026-2030) for holders of investigation permits, concessions and mining waste recovery rights.
  • 10 March 2026: the Council of Ministers approves the I Plan de Acción para la Gestión Sostenible de las Materias Primas Minerales 2026-2030 (€414 million and 34 measures) and the Programa Nacional de Exploración Minera 2026-2030 (€182 million). The plan provides for amending the Mining Act.
  • 25 March 2025: 1st list of 47 European strategic projects, 7 in Spain.
  • Upcoming, 24 November 2026: deadline to submit the study on critical raw materials in extractive waste (art. 27 of the CRMA).

Which section of the Spanish Mining Act covers rare earths, lithium or tungsten?

Ley 22/1973, de Minas (the Spanish Mining Act) divides all mineral resources into 4 sections. Section A covers resources of low economic value and geographically restricted marketing, as well as those that are merely extracted, crushed and sized for construction works (such as aggregates). Section B covers mineral and thermal waters, underground structures and deposits formed by previous mining operations, such as spoil heaps and tailings ponds. Section C is the residual clause: everything not included in the other sections. Section D covers coal, radioactive minerals, geothermal resources, bituminous rocks and anything the Government declares to be of energy interest.

The Act does not name rare earths, lithium or tungsten. In a natural deposit that is neither radioactive nor of energy interest, they fall under Section C, which is the section covered by this guide. This is an interpretation of the residual clause: no official text classifies a specific deposit in advance, and the mining authority determines the section during the application process.

There are 2 nuances worth bearing in mind. Radioactive minerals are governed by the Mining Act only in matters not regulated by the Ley de Energía Nuclear (the Spanish Nuclear Energy Act), meaning that a deposit with associated radioactive minerals requires analysing its legal fit before applying for anything. Furthermore, liquid and gaseous hydrocarbons fall outside the scope of the Mining Act.

All naturally occurring deposits are public domain property. Owning the land does not give you the right to exploit the minerals beneath it: that right is granted by the Spanish Administration through a permit or a concession.

As of 15 October 2026, there is no new Mining Act. The consolidated text of Ley 22/1973 in the BOE (Spain's Official State Gazette) has remained unchanged since 2014. The I Plan de Acción para la Gestión Sostenible de las Materias Primas Minerales 2026-2030 (1st Action Plan for the Sustainable Management of Mineral Raw Materials 2026-2030), approved on 10 March 2026, provides for amending it to integrate the European Critical Raw Materials Act (CRMA), but today the longstanding law still applies.

Exploration permit vs investigation permit vs exploitation concession in Spain

There are 3 tiers, and each has its own size, duration and surface fee. The exploration permit allows studies and reconnaissance that do not substantially alter the land over a large area: from 300 to 3,000 mining grids. It lasts 1 year, extendable by at most 1 more year, and where there are multiple applicants, the order of submission prevails.

Its value lies in priority: the holder can subsequently apply for investigation permits or direct concessions over the land within their perimeter that was free and registerable when the exploration application was submitted. This priority right must be exercised within the timeframe set by the Regulations, which the Act stipulates cannot be less than 1 month after the permit expires.

The investigation permit authorises works to uncover and define the resource (such as drilling or galleries) and grants the right, once defined, to be awarded the concession. It covers from 1 to 300 mining grids and lasts a maximum of 3 years.

The exploitation concession is the right to extract and use the resource. It covers from 1 to 100 mining grids, lasts 30 years and grants rights to all Section C resources within its perimeter, except those reserved by the State. Only 1 Section C concession can exist over the same piece of land.

The unit of measurement for all 3 is the mining grid (cuadrícula minera), measuring 20 sexagesimal seconds per side. Concessions are always granted in whole grids.

How to apply for a mining investigation permit in Spain and where to file

In practice, the application is processed before the mining authority of the autonomous community where the land is located. In the Community of Madrid, for example, this is the Dirección General de Promoción Económica e Industrial (Directorate-General for Economic and Industrial Promotion), which accepts online or in-person submissions and requires a power of attorney proving representation. If the resource spans land in 2 or more autonomous communities or on the continental shelf, the decision rests with the Central State Administration through the Ministerio para la Transición Ecológica, MITECO (Ministry for the Ecological Transition).

The land must be free and registerable (franco y registrable), meaning it is not already covered by another mining right that prevents it. The application designates the grids and is accompanied by the investigation project, including the work programme, the investment budget and the economic study of its financing. The Reglamento General para el Régimen de la Minería, Real Decreto 2857/1978 (General Regulations for the Mining Regime) grants 60 days from the submission of the application to complete the documentation, and requires the project to be signed by a mining engineer or technical mining engineer. Processing expenses are borne by the applicant.

The application must also include the restoration plan for the affected area, which is not a subsequent step: without an authorised plan, the permit is not granted (as explained below). Furthermore, if the Administration considers the financing unviable, it may require a bond of 10% of the planned investment for the 1st year.

Once the application is definitively admitted, a public consultation period is opened in the BOE and in the official provincial gazette. From publication in the BOE, there are 15 days to file objections, after which no objections are admitted.

The permit is granted for the requested period, up to a maximum of 3 years. It may be extended for 3 more years and, exceptionally, for successive periods, assessing the holder's solvency, the work carried out, the investments made and the results.

Processing fees (tasa, official fee) are currently set by the autonomous communities. The 1978 Regulations still express them in pesetas, and each region has its own fees law: in Madrid it is tariff item 356, with no published amount on the online portal's information sheet. Managora submits the application using your power of attorney, organises the file, responds to official requests and monitors deadlines; the technical project and the restoration plan are signed by a competent technician, as required by law.

How long a Spanish mining concession lasts, renewals and annual surface fees

There are 2 routes to obtaining a concession. A derived concession is requested when the investigation sufficiently proves the resource, and always within the validity period of the investigation permit: if you let the permit expire, you lose the right. It is requested with an exploitation project (work programme, investment budget and financing study), and the Administration verifies the existence of the resource on site.

A direct concession is requested without a prior investigation permit in 2 cases: when the resource is already evident and its exploitation is deemed viable, or when there is sufficient data on resources from expired mining rights which, due to technological improvements or new market prospects, allow their exploitation to be defined. A technical report must be added justifying why the direct route is appropriate.

Both files undergo public consultation and are resolved following a report from the Instituto Geológico y Minero de España (Geological and Mining Institute of Spain). If denied because the resource is not sufficiently proven, the applicant has 60 days to apply for an investigation permit over that land.

A Section C concession lasts 30 years and may be extended for equal periods up to a maximum of 90. Each extension requires demonstrating in the file the continuity of the resource or the discovery of a new one, and that extraction techniques have been adapted to technological progress. If a different resource of interest appears, it must be reported immediately.

In addition to the processing tasa, each right pays an annual surface fee (canon de superficie) per grid to the State: €1.2 in the exploration permit, €22.5 in the investigation permit and €45 in the exploitation concession granted under Ley 22/1973. The investigation and concession fees accrue on 1 January each year for rights existing on that date, whether work is carried out or not; the exploration fee accrues on the day the right is born.

Breaching the Mining Act is expensive: fines of up to €30,000 for minor infringements, up to €300,000 for serious infringements and up to €1,000,000 for very serious infringements.

Environmental impact assessment and restoration plan requirements for mining in Spain

It depends on the project. An ordinary environmental impact assessment (Annex I of Ley 21/2013, the Spanish Environmental Assessment Act) is required for open-cast mines affecting more than 25 hectares or moving more than 200,000 cubic metres of earth per year, those exploiting substances that may generate acidity or toxicity, such as sulphides or radioactive minerals, and certain underground mines. A simplified assessment (Annex II) applies to investigation projects with a pilot face, galleries or mining waste facilities, and exploitations not listed in Annex I.

In the ordinary procedure, public consultation lasts at least 30 working days and the environmental impact statement is issued within 4 months. The report for the simplified procedure is issued within 3.

The restoration plan is submitted alongside the permit or concession application. It includes the mining waste management plan and the location of its facilities, the proposed financial guarantee and, where an environmental assessment applies, proof of having processed it. The applicant must also prove sufficient economic, financial and technical solvency to fulfil it.

It is authorised at the same time as the mining title, following a prior report from the environmental authority, and becomes a special condition of that title. Beforehand, it undergoes public consultation for at least 30 days; if the project requires an environmental impact assessment, 1 single public consultation serves for both.

Once the title is granted, work cannot begin until 2 financial guarantees are put in place: 1 to rehabilitate the land of the exploitation and another for the mining waste facilities, which is not required for inert waste, non-hazardous non-inert waste or unpolluted soil, unless deposited in a Category A facility. They are calculated by the mining authority and may be set up via cash deposit, bank guarantee or insurance. The rehabilitation guarantee is reviewed annually according to what has already been restored, and its release is not automatic: upon completion, the operating entity must request it in writing.

The mining authority inspects at least 1 time a year from the start of mining operations, including after the closure of waste facilities. Managora can submit the application for authorisation of the plan using your power of attorney and, at the end, the request for the release of the guarantees; the technical content of the plan and its calculation are signed by a competent technician.

How to object or submit written submissions (alegaciones) against a mining permit or concession

If you own a property within the perimeter, hold an adjoining mining right, or are an affected local council or resident, you have several windows of opportunity, and all of them are short. The 1st is the public consultation for the permit or concession: 15 days from publication in the BOE. Once this deadline has passed, no objection is admitted, even if the notice is published in the provincial gazette later.

The 2nd is the public consultation for the environmental impact assessment, if the project requires one: at least 30 working days. The 3rd is that of the restoration plan, of at least 30 days, which coincides with the previous one when there is an environmental assessment.

An effective written submission (alegación) goes beyond a generic rejection. It is backed by proof of property ownership (land registry extract or title deed), the map or coordinates of the perimeter, and what the file fails to justify: land that is not free, overlaps with other rights, unguaranteed financing, shortcomings in the restoration plan or unstudied environmental effects.

Managora drafts the written submissions (alegaciones) or formal objection and submits them using your power of attorney within the deadline. This corresponds to our service sheet for written submissions (alegaciones) against a mining permit: you can view the updated fee on the sheet. It is advisable to instruct us on the very day you see the notice, as 15 days pass very quickly.

Strategic mining projects in Spain under the EU CRMA and Real Decreto 731/2026

These are 2 distinct statuses that are often confused. A European Strategic Project is recognised by the European Commission under Reglamento (UE) 2024/1252 (CRMA). It is only available for the 17 strategic raw materials listed in Annex I, including battery-grade lithium, tungsten and rare earths for permanent magnets, which form 1 single entry. Critical raw materials in Annex II (34 in total) that are not strategic, such as antimony, do not qualify for this status.

The application is submitted by the promoter to the Commission using the single template set out in Reglamento de Ejecución (UE) 2025/2194 (Implementing Regulation), and contains, among other things, the resource classification according to the United Nations Framework Classification, the permitting timetable, a public acceptance plan, the business plan and job estimates. The Commission decides within 90 days from when the application is complete, extendable by another 90, and the affected Member State may object and block recognition. The next call for applications is announced for late 2026.

Recognition does not replace any permit or the environmental assessment, but it caps the processing time: 27 months if the project includes extraction and 15 if it is only processing or recycling (24 and 12 if it was already being processed), extendable by 6 and 3 months in exceptional cases. The time taken by the promoter to prepare the environmental impact study does not count towards this limit. The clock starts when the single point of contact acknowledges that the application is complete, for which it has 45 days. Furthermore, the project is considered to be of public interest.

In Spain there is 1 point of contact per autonomous community (in Andalusia, the Dirección General de Minas; in Extremadura, the Dirección General de Industria, Energía y Minas; in Galicia, the Dirección General de Planificación Energética y Minas) and, for state-level projects or those spanning more than 1 region, 2 state bodies: the Subdirección General de Minas of MITECO for extraction and the Subdirección General para el Impulso de Proyectos Industriales of the Ministerio de Industria y Turismo (Ministry of Industry and Tourism) for processing and recycling. Spain has 7 projects on the 1st list (March 2025) and 2 on the 2nd (9 October 2026).

The Spanish status is different: Real Decreto 731/2026 (Royal Decree), in force since 18 September 2026, allows extraction, processing or circular economy projects involving critical raw materials to be declared a Proyecto Estratégico de Inversión (Strategic Investment Project). Applications may be submitted from the date to be determined, once the electronic systems are enabled and the scoring criteria and methodology are published. The application is filed online before the portal of the Comité de Inversiones Estratégicas (Strategic Investments Committee), with a statement of compliance confirming that the applicant is up to date with Hacienda (the Spanish Tax Agency) and the Seguridad Social (Spain's Social Security system); the preliminary declaration arrives in 1 month and the final declaration, from the Comisión Delegada del Gobierno para Asuntos Económicos (Government Delegated Commission for Economic Affairs), in 3 months, with administrative silence meaning rejection. Purchases of shares or equity stakes, capital increases or reductions, and structural corporate modifications are excluded.

Managora prepares the European application, which the promoter sends from their own account on the Commission's portal, and submits the Real Decreto 731/2026 application using your power of attorney. We cover this in detail in our guide on the European Critical Raw Materials Act.

The extractive waste study due by 24 November 2026 under Article 27 CRMA

This is an obligation under Article 27 of the CRMA with a fixed deadline. Operators required to have a mining waste management plan must submit to the mining authority, no later than 24 November 2026, a preliminary economic assessment study regarding the potential recovery of critical raw materials from the waste stored in their facility and from the waste being generated.

The study must include at least an estimate of the quantities and concentrations of critical raw materials, the methods used to estimate them, and an assessment of the technical and economic feasibility of recovering them. New facilities must submit it alongside their waste management plan.

There is an exemption: operators are exempt if they demonstrate to the authority, with a high level of certainty, that their waste does not contain technically recoverable critical raw materials. Closed or abandoned facilities are not the responsibility of the operator: they are entered into a database that the State must create.

If you subsequently wish to exploit a spoil heap or tailings pond that is undergoing closure or is already closed, the route is governed by the Mining Act: first, the declaration of the resource as Section B, which is announced in the provincial gazette with 30 days of public consultation; if the facility is still active, an authorisation from the competent authority suffices. The content of the study is technical and geological; Managora compiles the file using your technician's data and submits it using your power of attorney before the mining authority of your autonomous community.

Step by step

  1. 1

    Confirm the section and check that the land is free(Before applying)

    Verify that the resource falls under Section C and that the grids are free and registerable, with no overlaps with other mining rights.

  2. 2

    Choose the right you need(Before applying)

    Exploration (300 to 3,000 grids, without altering the land), investigation (1 to 300 grids) or direct concession if the resource is already evident.

  3. 3

    Submit the application to the mining authority(Submission date: in exploration, this sets priority)

    Application designating the grids, power of attorney and proof of payment of the regional tasa, filed before the autonomous community (or MITECO if it affects 2 or more communities or the continental shelf).

  4. 4

    Complete the project and the restoration plan(60 days from the application)

    Investigation project signed by a mining engineer or technical mining engineer (programme, budget and financing) and restoration plan with proposed guarantees.

  5. 5

    Apply for the environmental assessment if applicable(Report in 3 months (simplified); statement in 4 months (ordinary))

    Simplified if there is a pilot face, galleries or waste facility; ordinary in the cases listed in Annex I of Ley 21/2013.

  6. 6

    Follow the public consultation period(15 days for objections from the BOE notice)

    Notice in the BOE and in the provincial gazette. Respond to objections and official requests from the Administration.

  7. 7

    Set up the guarantees and pay the surface fee(Before starting work)

    Without the financial guarantees of the restoration plan (the waste guarantee is not always required), work cannot begin. The surface fee accrues every 1 January.

  8. 8

    Apply for the concession before the permit expires(Within the validity period of the permit)

    Once the resource is proven, apply for the derived concession with an exploitation project. If there is not enough time, apply for a permit extension beforehand.

A worked example

A company applies for a 3-year investigation permit covering 100 grids for a tungsten prospect. The mining authority considers the financing unclear and requires a bond; the planned investment for the 1st year is €400,000. In the 3rd year, the company proves the resource and applies for a derived concession covering 20 grids.

  • Investigation permit surface fee: 100 grids x €22.5 = €2,250 per year.
  • 3 years of permit: €2,250 x 3 = €6,750 in surface fees, whether work is carried out or not.
  • Bond for doubtful financing: 10% of €400,000 = €40,000.
  • Concession surface fee: 20 grids x €45 = €900 per year, accruing every 1 January.
  • Added to these amounts are the regional processing tasa and the restoration plan guarantees, which are calculated by the mining authority.

The fixed cost of maintaining the mining right is low compared to the investment, but the bond and restoration guarantees tie up capital from the outset. And the concession must be requested before the end of the 3rd year.

Section C mining rights: size, duration and annual surface fee

RightAreaDurationExtensionFee per grid and year
Exploration permit300 to 3,000 grids1 yearAt most, 1 more year€1.2 (accrues when the right is born)
Investigation permit1 to 300 gridsUp to 3 years3 more years and, exceptionally, successive periods€22.5 (accrues every 1 January)
Exploitation concession1 to 100 whole grids30 yearsFor equal periods up to a maximum of 90 years€45, concession granted under Ley 22/1973 (every 1 January)

Key deadlines in the mining and environmental procedure

StepDeadlineRegulation
Complete investigation permit documentation60 days from the applicationRD 2857/1978, art. 66
Objection during public consultation for the permit or concession15 days from publication in the BOERD 2857/1978, art. 70
Apply for an investigation permit after a concession is denied for lack of proof of the resource60 daysLey 22/1973, art. 65
Public consultation for the ordinary environmental impact assessmentAt least 30 working daysLey 21/2013, art. 36.1
Environmental impact statement (ordinary) / report (simplified)4 months / 3 monthsLey 21/2013, arts. 33.4 and 47.1
Public consultation for the restoration planAt least 30 daysRD 975/2009, art. 6.3
Public consultation for declaring mining waste as Section B30 daysRD 2857/1978, art. 46.2
Study of critical raw materials in extractive wasteUntil 24 November 2026Reglamento (UE) 2024/1252, art. 27.3
Authorisation of a European Strategic Project27 months with extraction; 15 processing or recycling onlyReglamento (UE) 2024/1252, art. 11.1
Strategic Investment Project (Proyecto Estratégico de Inversión)Preliminary declaration in 1 month; final in 3 months, rejection by administrative silenceRD 731/2026, arts. 16.6 and 17.5

European Strategic Project (CRMA) vs Strategic Investment Project (RD 731/2026)

CRMA Strategic ProjectStrategic Investment Project
Who grants recognitionThe European Commission; the affected Member State can block itThe Comité de Inversiones Estratégicas (preliminary) and the Comisión Delegada del Gobierno para Asuntos Económicos (final)
Eligible materialsThe 17 strategic raw materials in Annex ICritical raw materials (extraction, processing or circular economy) and net-zero technologies, among others
Who submitsThe promoter, from their account on the Commission portalThe promoter or their accredited representative, online
Decision timeframe90 days from complete application, extendable by 901 month preliminary and 3 months final; rejection by administrative silence
Benefits provided27- or 15-month cap for authorisations, single point of contact and public interest statusNational declaration as a strategic project
When to applyDuring an open call; the next one is in late 2026No call required, from the date to be determined once the online portal is enabled and the scoring criteria and methodology are published
What Managora doesPrepares the application; the promoter sends itPrepares and submits it using your power of attorney

Official forms and where it is filed

Frequently asked questions

Can I investigate or extract minerals on my own land without a permit?

No, except for occasional extraction of minor importance carried out by the landowner for their exclusive use and without mining techniques. Naturally occurring deposits are public domain: the right to investigate or exploit them is granted by the Administration through a permit or concession, not by land ownership.

How long does it take to get a decision on an investigation permit?

Neither the Mining Act nor the regional procedure sheet we consulted sets a single resolution deadline, and it depends heavily on whether the project requires an environmental assessment (4 months for the impact statement in the ordinary procedure and 3 for the report in the simplified procedure, plus public consultation). What is fixed are the 60 days to complete the documentation and the 15 days for objections from publication in the BOE.

What happens if my investigation permit expires before I apply for the concession?

You lose the right to the derived concession: it can only be requested within the validity period of the permit. If the permit is close to expiring and the investigation is not finished, the proper course of action is to apply in time for an extension, of up to 3 years, justifying the work carried out and the investments made.

Is the annual surface fee payable even if I have not carried out any work during the year?

Yes. For both the investigation permit and the concession, it accrues on 1 January each year for the rights existing on that date, whether there is activity or not: €22.5 per grid for investigation and €45 for a concession granted under Ley 22/1973. For the exploration permit, it is €1.2, accruing from the day the right is born.

Does being a European Strategic Project exempt me from the environmental assessment or the mining permit?

No. Recognition does not exempt you from any authorisation. What it provides is a maximum processing timeframe (27 months with extraction, 15 with processing or recycling only), a single point of contact and public interest status. The time taken by the promoter to prepare the environmental impact study does not count towards those deadlines.

I am a foreign company: can I apply for a mining permit in Spain?

Anyone who meets the conditions to hold mining rights set out in the Mining Act itself, to which Article 43 refers, may apply. Managora submits the application using your power of attorney and prepares the file in Spanish in accordance with the requirements of the mining authority.

We handle the whole procedure for you, from start to finish.

You describe your case in a chat and sign; we file it with the Spanish authorities. Fixed price from €399.00 (21% VAT included), plus the tasa (official fee) where there is one.

See the procedure

Related procedures

The price, the tasa (official fee) and the current deadlines are on each procedure page.

Managora for Import / Export

Your international trade, prepared and defended: TARIC code, duties and import VAT before you buy, binding tariff information, EORI, AEO (OEA) certification, dual-use licences, end-user certificate for China, Intrastat and Modelo 349 (EU sales list). The customs declaration is lodged by your company or by a registered customs representative.

See the package →

If you are refused or need to appeal

Handled by Managora's law firm.